Clenergy completes a 30MW PV power plant in Ningxia, China

Clenergy, a leading solar solution provider, successfully connected a 30MW PV system to the local power grid in Zhongwei which is located in the Ningxia Province in central China.

Clenergy, a leading solar solution provider, successfully connected a 30MW PV system to the local power grid in Zhongwei which is located in the Ningxia Province in central China. The project, which was wholly financed by Clenergy, is the first large-scale grid-connected PV power plant in Ningxia constructed by Clenergy Engineering, the companys engineering subsidiary. The vast stretches of blue PV panels are a unique, visually pleasing addition to the scenery of Chinas western desert.


Construction on the 270-million-yuan project started in October 2014. Engineers and technicians from Clenergy Engineering worked under difficult geographical conditions and in harsh weather with winter night temperatures sometimes dropping below −30 °C (−22 °F). Despite the tight schedule and the challenging engineering tasks, the passionate experts of Clenergy Engineering completed the project in three months with no compromises to quality.

The projects strict quality control measures included different project monitoring and risk reduction techniques such as daily site inspections and real-time problem rectification. Upon the successful connection to the grid, Clenergy handed over the operations to its client, one of Chinas major PV companies.

"The successful completion and grid connection of this large-scale solar power plant is a good platform for demonstrating Clenergys capabilities. It demonstrates our strengths and know-how which helped us winning more opportunities," said Clenergys CEO Daniel Hong. He also noted the positive impact this project had on the areas energy portfolio and on its ecological environmental protection through burning less fossil fuel.

This 30MW system generates over 42 million kilowatt hour of electricity, saving approximately 12747.9 tonnes of standard coal and 42295.93 tonnes of carbon dioxide per annum.

Clenergy will continue strengthening its capabilities in solar PV and promoting clean renewable energy developments in 2015 and beyond.





About Clenergy

Clenergy (www.clenergy.com) is a technology company in the solar PV industry, with its headquarters in Xiamen, China, and branch offices in Australia, Japan, the United Kingdom, and the United States, and a regional office in Malaysia. Clenergy designs, manufactures and distributes a range of renewable energy products, including solar PV mounting products, inverters and power electronic equipment, which address the needs of residential, commercial and utility scale customers.
Clenergy is an ISO 9001 accredited company and all of its products comply with international standards. It is through its focus on innovation, quality and service that Clenergy has achieved rapid growth and built a strong international reputation. Clenergys products and solutions are marketed and distributed through a worldwide network of strategic partners and distributors. For more information, please visit www.clenergy.com

Featured Product

Vecoplan - Planning and implementation of complete processing plants in refuse derived fuel production

Vecoplan - Planning and implementation of complete processing plants in refuse derived fuel production

In order to reduce the costs involved in the energy-intensive production of cement, many manufacturers are turning to refuse-derived fuels (RDF), considerably reducing the proportion of expensive primary fuels they would normally use. Solid fuels are being increasingly used - these might be used tyres, waste wood or mixtures of plastics, paper, composite materials and textiles. Vecoplan provides operators of cement plants with proven and robust components for conveying the material and separating iron and impurities, efficient receiving stations, storage systems and, of course, efficient shredders for an output in various qualities.